- The Developments Schedule
2005: | Initial Appraisal and Concept Development with Eifion Bowen Head of Planning. |
2005-2008: | Preparation of farm infrastructure and concept development. |
2009-2011: | Construction of farm workshop, Blaencwm. |
2011: | First draft of Financial Plan and Legal framework. |
2012-2013: | Construction of Longbyre building, Blaencwm. |
2012-2013: | Assessments of existing UK and international facilities, creating contacts list and Business Plan. |
2013: | Prepare infrastructure for yurt village. |
2013: | Construction of wide span building for school activities, Waunlas. |
2014: | Conversion of Waunlas farm building for toilet and shower facilities. |
2014: | First trial courses. |
As of 2013 we are on schedule!